National Electrical Installation Standards

Standards as High as Your Own

 
?
Tuesday, November 7, 2023

Question:

Hello Charlie, I disagree with your answer to the question for September 29, 2023. A building under construction that did not exist prior to the adoption of the current code, would NOT be considered an existing buildings or structures per the definition in the International Existing Building Code.

As such, the provisions of the exception in Section 250.50 would not be applicable. Since 250.50 specifically requires all electrodes, present be used the AHJ would be correct to require the rebar be exposed for connection of the concrete encased electrode.

It is up to the builder to ensure that the electrician is involved prior to the pouring of the footing or otherwise making the connection accessible. Regards, Jeff Bower
A

Answer:

Hi Jeff, thanks providing your opinion on the application of the Exception to Section 250.50. In general, the definition of an “Existing Building” found in the IEBC would not have any bearing on the application of the rules found in the NEC®. The exception found in Section 250.50 was specifically included by CMP 5 to provide relief for situations where the foundation/footings were completed before the electrical contractor was onsite, or in some cases before the electrical contractor was even hired. The exception provides latitude for the local AHJ to use discretion in the application of this requirement based on the circumstances. States and local Municipalities may enforce it differently based on statute or ordinances, which is why it is always important to check with the local AHJ.  

ABOUT CQD: The Code Question of the Day (CQD) is NECA and ELECTRICAL CONTRACTOR Magazine’s flagship National Electrical Code (NEC®) public forum for the industry, sponsored by EATON. The daily distribution of Q&A generates a lively dialogue and shares relative Code-based practical responses.

SUBMIT YOUR CODE QUESTION: Click here to submit a question to for inclusion in an upcoming edition of the Code Question of the Day, or email codequestion@necanet.org

CHARLIE TROUT: Charles M. Trout, better known as Charlie, was a nationally known NEC® expert and author. He served on several NEC® technical committees and is past chairman of CMP-12. In 2006 Charlie was awarded the prestigious Coggeshall Award for outstanding contributions to the electrical contracting industry, codes and standards development, and technical training. Even though Charlie passed away in October of 2015, his work continues in spirit. NECA continues to maintain this question forum for its many subscribers in memory and recognition of all his significant contributions to making the NEC what it is today.

NECA STANDARDS: NECA publishes the National Electrical Installation Standards™ (NEIS™), a series of ANSI-approved performance and quality standards for electrical construction. NEIS can be purchased in the NECA Store in three formats: a printed or  PDF download of a standard or, as an  annual subscription service.

NECA SAFETY PRODUCTS & PUBLICATIONS: NECA produces electrical safety publications and products for the industry including jobsite safety guides, handbooks and resource kits. View a full listing of available resources and products »

IMPORTANT NOTICE: Unless the question requests a response based on a specific edition, all answers are based on the latest edition of NFPA 70® National Electrical Code®.

This correspondence is not a formal interpretation of the NEC® and any responses expressed to the questions are opinions and do not necessarily represent the official position of NECA, NFPA, the NEC Correlating Committee any Code-making panel or other electrical technical committee. In addition, this correspondence is neither intended, nor should it be relied upon, to provide professional consultation or services. 

UPDATE YOUR SUBSCRIPTION PREFERENCES: Subscribe or Unsubscribe from this list.