Question:

Can I come the bottom of meter can to a bus bar and then come from bus bar to the house load control center. Then from bus bar to a outdoor breaker box?

Thanks, Kaleae Groene

A

Answer:

Hey Kaleae thanks for your question. If I understand what you are describing correctly you are planning to install wire type conductors from a meter socket enclosure to a busway as that term is defined in 368.2. The busway would then be connected to a paneboard used as service equipment (house load control center?) for a house and another panelboard (located outdoors) also used as service equipment. Busways are allowed to be used as service-entrance conductors as stated in 230.43(9) and spliced are allowed as stated in 230.46. The busway would need to be outside the building because service conductors are not allowed to pass through the interior of a building or structure if used to supply a different building or structure (outdoor breaker box) as stated in 230.3. Both service disconnecting means need to be grouped at the same location as stated in 230.40 Exception No. 2, 230.71(A), and 230.72.

So if you can comply with all of the rules it seems possible to do what you are asking but unless there is something special about the installation a different design might be better and less expensive.

ABOUT CQD: The Code Question of the Day (CQD) is NECA and ELECTRICAL CONTRACTOR Magazine’s flagship National Electrical Code (NEC®) public forum for the industry, sponsored by EATON. The daily distribution of Q&A generates a lively dialogue and shares relative Code-based practical responses.

SUBMIT YOUR CODE QUESTION: Click here to submit a question to for inclusion in an upcoming edition of the Code Question of the Day, or email codequestion@necanet.org

CHARLIE TROUT: Charles M. Trout, better known as Charlie, was a nationally known NEC® expert and author. He served on several NEC® technical committees and is past chairman of CMP-12. In 2006 Charlie was awarded the prestigious Coggeshall Award for outstanding contributions to the electrical contracting industry, codes and standards development, and technical training. Even though Charlie passed away in October of 2015, his work continues in spirit. NECA continues to maintain this question forum for its many subscribers in memory and recognition of all his significant contributions to making the NEC what it is today.

NECA STANDARDS: NECA publishes the National Electrical Installation Standards™ (NEIS™), a series of ANSI-approved performance and quality standards for electrical construction. NEIS can be purchased in the NECA Store in three formats: a printed or  PDF download of a standard or, as an  annual subscription service.

NECA SAFETY PRODUCTS & PUBLICATIONS: NECA produces electrical safety publications and products for the industry including jobsite safety guides, handbooks and resource kits. View a full listing of available resources and products »

IMPORTANT NOTICE: Unless the question requests a response based on a specific edition, all answers are based on the latest edition of NFPA 70® National Electrical Code®.

This correspondence is not a formal interpretation of the NEC® and any responses expressed to the questions are opinions and do not necessarily represent the official position of NECA, NFPA, the NEC Correlating Committee any Code-making panel or other electrical technical committee. In addition, this correspondence is neither intended, nor should it be relied upon, to provide professional consultation or services. 

UPDATE YOUR SUBSCRIPTION PREFERENCES: Subscribe or Unsubscribe from this list.