Question:

Need to install a remote (not remote controlled) breaker from my 800 amp panel to a 200 amp sub panel. I believe the remote breaker needs to be 6 feet away from the 800 amp panel per code. Is it a minimum of 6 feet away, or 6 feet of total wire length away from the 800 amp panel?

Michael Smith

A

Answer:

Hey Michael thanks for your question. There are various rules in the NEC that use 6 ft as a dimension but none seem applicable to the situation you are describing. If the conductors supplying the 200 amp panelboard have overcurrent protection as stated in 240.4 there is no dimension provided.  If you are using one of the "tap rules" in 240.21 to locate the overcurrent protective device other that at the point where the conductor receives its supply, then the dimensions in the specific rule (such as 10 ft, 25 ft, etc) apply.

ABOUT CQD: NECA’s Code Question of the Day (CQD) is a leading National Electrical Code® forum for NECA and the industry. The CQD generates a lively dialogue and relative practical and Code-based responses to an ever-increasing and interactive audience.

IMPORTANT NOTICE: All answers are based on the latest edition of the National Electrical Code®, unless the question requests a response based on a specific edition. This correspondence is not a formal interpretation of the NEC®. Any responses expressed to the questions are opinions and do not necessarily represent the official position of NECA, NFPA, or any technical committee. In addition, this correspondence is neither intended, nor should it be relied upon, to provide professional consultation or services.

ABOUT CHARLIE: Charles M. Trout, better known as Charlie, was a nationally known NEC® expert and author. He served on several NEC® technical committees and is past chairman of CMP-12. In 2006 Charlie was awarded the prestigious Coggeshall Award for outstanding contributions to the electrical contracting industry, codes and standards development, and technical training. Charlie was also a member of NECA’s Academy of Electrical Contracting. Charlie’s experienced team of industry experts keep the CQD dialogue and discussions active and informative in the spirit of the man himself, as he wanted.

NECA STANDARDS: NECA publishes the National Electrical Installation Standards™ (NEIS™), a series of ANSI-approved performance and quality standards for electrical construction. Visit NECA-NEIS.org for more information. NEISÔ can be purchased in three formats: as paper books, on CD, or as electronic downloads.

NECA SAFETY PRODUCTS: NECA publishes valuable electrical safety books and CDs for the industry. Visit necanet.org/store to view or purchase NECA safety products.

 CONTACT US: To submit a Code question, subscribe, or unsubscribe from this list, please e-mail: codequestion@necanet.org.