National Electrical Installation Standards

Standards as High as Your Own

 
?
Wednesday, January 2, 2019

Question:

Re: CQD answer published Wed, December 19, 2018 -Meter Disconnect Switches

"Charlie" no need to publish my comments but it seems Carl the questioner is mixing apples and oranges. The cold sequencing switch is indeed required in NJ for certain size services but I am not sure it has to have an AIC rating since it is a non-fused switch. The disconnect that is immediately after the meter socket is the one that is a fused switch (or it could actually be a circuit breaker if someone desired that) and that is the one which requires the AIC rating. Also the grounding electrodes and grounding electrode conductors do not appear until the main disconnect is reached. There are no grounding conductors to be installed in the cold sequencing switch. The cold sequencing switch is strictly a safety to be used by the utility to allow their employees to remove and install the meters while not under load. Another point is that the cold sequencing switch is bonded by the neutral or ungrounded conductor similar to the meter socket or CT cabinet bonding. Looking forward t tomorrows response. Keep up the good work and Merry Christmas to all.

Rich Van Wert

A

Answer:

Rich thanks for your follow up comment and compliment. Meter disconnect switches are allowed on the supply side of the service disconnect as stated in 230.82(3). But they must have a short-circuit current rating (SCCR), as that term is defined in Article 100, at least that of the available short circuit current as stated in that section. True, the switches can be installed to help utility personnel do their work in a safer manner, but they are often part of premises wiring as that term is defined in Article 100 because they are on the load side of the service point, also defined in Article 100. As the submitter mentioned non-fusible enclosed switches are not available with SCCR's above 10 kA so if the available fault current exceeds that, the switch would need to be a fusible type to achieve that rating. See 110.9 and 110.10 for additional information.

ABOUT CQD: The Code Question of the Day (CQD) is NECA and ELECTRICAL CONTRACTOR Magazine’s flagship National Electrical Code (NEC®) public forum for the industry, sponsored by EATON. The daily distribution of Q&A generates a lively dialogue and shares relative Code-based practical responses.

SUBMIT YOUR CODE QUESTION: Click here to submit a question to for inclusion in an upcoming edition of the Code Question of the Day, or email codequestion@necanet.org

CHARLIE TROUT: Charles M. Trout, better known as Charlie, was a nationally known NEC® expert and author. He served on several NEC® technical committees and is past chairman of CMP-12. In 2006 Charlie was awarded the prestigious Coggeshall Award for outstanding contributions to the electrical contracting industry, codes and standards development, and technical training. Even though Charlie passed away in October of 2015, his work continues in spirit. NECA continues to maintain this question forum for its many subscribers in memory and recognition of all his significant contributions to making the NEC what it is today.

NECA STANDARDS: NECA publishes the National Electrical Installation Standards™ (NEIS™), a series of ANSI-approved performance and quality standards for electrical construction. NEIS can be purchased in the NECA Store in three formats: a printed or  PDF download of a standard or, as an  annual subscription service.

NECA SAFETY PRODUCTS & PUBLICATIONS: NECA produces electrical safety publications and products for the industry including jobsite safety guides, handbooks and resource kits. View a full listing of available resources and products »

IMPORTANT NOTICE: Unless the question requests a response based on a specific edition, all answers are based on the latest edition of NFPA 70® National Electrical Code®.

This correspondence is not a formal interpretation of the NEC® and any responses expressed to the questions are opinions and do not necessarily represent the official position of NECA, NFPA, the NEC Correlating Committee any Code-making panel or other electrical technical committee. In addition, this correspondence is neither intended, nor should it be relied upon, to provide professional consultation or services. 

UPDATE YOUR SUBSCRIPTION PREFERENCES: Subscribe or Unsubscribe from this list.