National Electrical Installation Standards

Standards as High as Your Own

 
?
Monday, February 6, 2023

Question:

Hello CQD, I'm an apprentice that's been really enjoying the CQD for about a year now, and we had a problem come up in class that sparked disagreement. The scenario is this:

With three 208V, 3-Phase, Design-B, CONT Duty, Squirrel Cage motors rated at 10 HP, 25 HP, and 30 HP, and all on a single branch circuit, which code section do you use to determine the maximum size of the Inverse-Time circuit breaker being used as the OCPD for the circuit?

It seems to me that 430.53(C)(4) indicates that Table 430.52 should be applied to the largest motor (30 HP, FLC determined by Table 430.250), and then the FLCs (per Table 430.250) of the other two motors should be added -- without a multiplier -- to that product. Finally, the next breaker size down per Table 240.6(A) should be chosen. Thanks, Ira Wahlmeier
A

Answer:

Hi Ira, glad to hear you are enjoying the CQD, and kudos to you for taking such an interest in the NEC®. It sounds like you are on the right track. Section 430.53 provides general guidance on installations of multiple motors and/or loads on one branch circuit.

 Sections 430.53(A)-(D) are applied based on the installation applications.

 To apply Section 430.53(C), you must meet the criteria listed in the charging text requiring factory assembly or field installed:

  • Controller(s)
  • Overload Devices
  • Branch-circuit, short-circuit and ground-fault devices

     To answer the question yes, Section 430.53(C)(4) would be used to determine the rating of Fuses or Inverse Time CB. The branch-circuit OCPD shall have a rating not exceeding that specified in Section 430.52 for the largest motor (30HP) plus the SUM of the full-load current rating of the other motors connected to the branch circuit (10HP & 25HP) found in Table 430.250. If the calculated value is less than the ampacity of the branch circuit conductors, the OCPD can be increased in accordance with Section 240.4(B).

    Keep in mind that the other conditions: (1), (2), (3), (5) and (6) would all need to be met as well to utilize Section 430.53(C).

ABOUT CQD: The Code Question of the Day (CQD) is NECA and ELECTRICAL CONTRACTOR Magazine’s flagship National Electrical Code (NEC®) public forum for the industry, sponsored by EATON. The daily distribution of Q&A generates a lively dialogue and shares relative Code-based practical responses.

SUBMIT YOUR CODE QUESTION: Click here to submit a question to for inclusion in an upcoming edition of the Code Question of the Day, or email codequestion@necanet.org

CHARLIE TROUT: Charles M. Trout, better known as Charlie, was a nationally known NEC® expert and author. He served on several NEC® technical committees and is past chairman of CMP-12. In 2006 Charlie was awarded the prestigious Coggeshall Award for outstanding contributions to the electrical contracting industry, codes and standards development, and technical training. Even though Charlie passed away in October of 2015, his work continues in spirit. NECA continues to maintain this question forum for its many subscribers in memory and recognition of all his significant contributions to making the NEC what it is today.

NECA STANDARDS: NECA publishes the National Electrical Installation Standards™ (NEIS™), a series of ANSI-approved performance and quality standards for electrical construction. NEIS can be purchased in the NECA Store in three formats: a printed or  PDF download of a standard or, as an  annual subscription service.

NECA SAFETY PRODUCTS & PUBLICATIONS: NECA produces electrical safety publications and products for the industry including jobsite safety guides, handbooks and resource kits. View a full listing of available resources and products »

IMPORTANT NOTICE: Unless the question requests a response based on a specific edition, all answers are based on the latest edition of NFPA 70® National Electrical Code®.

This correspondence is not a formal interpretation of the NEC® and any responses expressed to the questions are opinions and do not necessarily represent the official position of NECA, NFPA, the NEC Correlating Committee any Code-making panel or other electrical technical committee. In addition, this correspondence is neither intended, nor should it be relied upon, to provide professional consultation or services. 

UPDATE YOUR SUBSCRIPTION PREFERENCES: Subscribe or Unsubscribe from this list.